What is the best practice to update the Original Estimate in Jira? -


i few clarification of original estimate field in jira.

i have started work 5d original estimate. after completion of second day, have logged 2d of work.

current: original estimate: 5d remaining estimate: 3d logged: 2d 

if want update original estimate 6d, whether need update original estimate field & remaining field

or updating original estimate field fine?

will updating original estimate in middle of work affect other fields?

helps appreciated.

what best practice update original estimate in jira?

to not.

the point of original estimate record how time team thought ticket take before work started. way actual time can compared original estimate , information can used team can better @ estimating.

if estimate changes, reflect in remaining estimate field. there highlight how more time think needed.


Comments

Popular posts from this blog

php - Vagrant up error - Uncaught Reflection Exception: Class DOMDocument does not exist -

vue.js - Create hooks for automated testing -

Add new key value to json node in java -